Hotels

Hotel W

Client
CIGAHOTELS ESPAÑA, S.L.U
Area
15.759m2
Delivery date
May 2018
Duration
4 moths

Thanks to work methodology and planning, the work was delivered one week before the agreed time:

– Daily planning with Pull Sessions with the associate suppliers; control of stocks, circulations, waste materials.

– Development of a quality control system in the factory and in receiving prior to installation.

– Deliveries with zero rework management.

– Day and night shifts for minimal interruption of hotel operation.